Scarborough councillors back construction staging on Kingston Road despite residents’ concerns.
On Nov. 25, The Scarborough Community Council voted to extend a construction staging area along Kingston Road, but residents and local business owners are concerned about disruptions and accessibility.
Our Documenter Gayathri Chandrarjah has all the details.
In the meeting, councillors and staff discussed a proposed 10-storey rental building with retail located on the ground floor at 2328-2350 Kingston Rd., near Sharpe Street in Scarborough Southwest.
The City’s Transportation Services department recommended closing part of the north sidewalk, boulevard and westbound curb lane along Kingston Road from Dec. 11, 2026 to Feb. 28, 2027 to accommodate the construction.
However, residents are concerned about ongoing disruptions especially after construction has already obstructed the entrances of local businesses, parking spaces and accessible loading zones that are used by residents and those relying on Wheel-Trans, according to a written submission by resident Karri Wong.
In the letter to Council, Wong also asked why construction staging had been ongoing since September under monthly street occupation permits before Council was asked to authorize the longer-term agreements. They also asked for the item to be deferred until the City could explain the original approval process.
During the meeting, Coun. Parthi Kandavel relayed concerns from local businesses about “trucks creating challenges” in the area. City staff said they spoke to the developers and hadn’t observed any violations.
Coun. Michael Thompson asked about the possibility of compensation for affected businesses and staff suggested that it could be discussed through the City’s Economic Development Committee.
Councillors did not discuss the written concerns about obstructions to accessibility loading zones, and unanimously voted to move forward with the extension. The decision will now go to City Council for consideration.
The development is expected to be completed in February 2028, while proposed construction staging is scheduled to end in February 2027.